|
News.......
Motor grader, Dozer
And GPS Boost Site Work Efficiency |
Tiger Contracting is
using GPS technology on a new motor grader and a new dozer to
complete site work on a 178,000-square-foot Lowes Home
Improvement Center project in Indian Harbour Beach, Fla. The
project also involved demolition and recycling of concrete on
the site.
"Productivity is the name of the game on this project," noted
project manager Scott Smith, adding that the company added a new
LeeBoy 685B motor grader and a Cat D5G dozer to assist with the
site work on the 15-acre site. Both machines were outfitted with
Trimble Model GCS900 GPS machine control systems. The Trimble
system uses the MS980 smart antenna — an integrated GPS receiver
and antenna — mounted to each end of the machine blade, and can
operate in a stakeless environment to an accuracy of 20
millimeters to 30 millimeters (0.1 foot).
"Technology, power and maneuverability are the factors that make
it happen for us on this job," Smith said.
Tiger subcontracted the job from Marcobay Construction, Inc.,
also from Lakeland. The work has a tight time line. It's made
even more challenging because the new center is being built on
the site of nine buildings damaged or destroyed during a recent
hurricane.
"At the same time we are preparing the site," adds Smith, "we
were crushing, processing and recycling a significant amount of
old onsite concrete material." This included old footers,
building pads and paving.
Demolition of the existing structures was handled by Cross
Environmental. Tiger then brought in a portable crusher and
screener to process the salvaged concrete into #57 stone, fines
and #4 aggregate, and to recover the steel. The #4 material was
used in the construction of an on-site storm vault. The #57
stone was used as bedding and backfill for underground utility
lines. The extra #57 stone and the fines were incorporated into
the construction of the building pad.
Smith noted that "equipment utilization and mobility" were two
major considerations on this project. According to site
superintendent Rick Mosley, the LeeBoy motor grader was
specifically selected for its ability to cope with tight working
areas. Normally fitted with a 10-foot sliding moldboard, it was
instead fitted with a longer 12-foot blade because it was felt
that the 15,200-pound machine with its 110-horsepower Cummins
diesel engine could handle the weight of the on-site sand and
processed stone.
Even though the site sounds large, he adds, its layout
complicated construction.
"That's where GPS and laser technology come in," Smith said,
adding that "15 acres sounds like a large area. However, by the
time we have much of the sitework done and the building laid out
it shrinks considerably in size. The subcontractors, demolition
contractor, the block layers, the underground utility
contractor, and the paving contractor all have their materials
and equipment here too. So the site shrinks significantly," he
continued.
During parking area construction, which has involved a large
amount of earthwork, Tiger has relied heavily on the GPS and
laser technology.
The extension of an existing large retention pond also utilized
the new Leeboy 685B motor grader and the Cat dozer and their
high-tech electronics. To reprofile and enlarge the existing
stormwater retention pond and reprofile the drainage pattern,
the contractor used a Komatsu PC200 excavator to outload the
stockpiled material into a Case rear dump hauler. The Cat dozer
and the LeeBoy motor grader, using the Trimble GPS system, then
spread the fill, which was compacted by a Bomag roller. Because
of the extremely dry weather, Tiger crews used two water trucks
almost constantly to rehydrate the soil.
Underground utilities, including a live 8-inch sewer line,
further complicated work. Most of the old lines had to be
removed before new lines could be installed.
Yet another aspect of the project was the addition of a 12-foot
wide turn lane to U.S. Route A1A to feed the Lowes complex.
Tiger Contracting used the LeeBoy to profile the subgrade and
add two 6-inch thick lifts of crushed limerock and to work in
and around several power poles that had yet to be relocated. The
12-foot moldboard was just right for the new 12-foot wide lane
and maneuvered easily around the obstructions. The Bomag roller
handled compaction.
With the summer rains and start of the 2007 hurricane looming
ever nearer, Tiger Contracting had its work cut out for it. But
heavy equipment and high-tech electronics helped it all to come
through on time.
"The faster we get the job done, the sooner they can open the
store for business and we can go on to our next project," Smith
said.
By Gini and Dan McKain
July 02, 2007
Dixie Contractor
|
|
|