A slide rail shoring system from
Efficiency Production helps East Tennessee Grading complete a
challenging lift station installation in Chattanooga, Tenn.
East Tennessee
Grading, Inc. of Chattanooga, Tenn., recently installed a new
precast lift station for the city of Chattanooga as part of an
overall upgrade to the sewer system. The installation was sited
in some challenging terrain, prompting the contractor to look at
new approaches to handling the installation.
East Tennessee
Grading was founded in 1989. The company specializes in site
grading and utility work on a variety of commercial,
residential, highways, airports, railroads, landfills, and water
and sanitary sewer projects.
On the
Chattanooga sewer upgrade project, East Tennessee Grading's
estimator and project manager Mike Brock looked at the details
of the project and determined that using traditional trench
boxes would not be the most cost-effective solution.
"The wet well
needed to be set much deeper than what we normally use trench
boxes to shore," Brock said. "I know other people who had used
slide rail systems before, and they advised that it might be an
option."
Brock worked with
Greg Ross, Efficiency Production's Slide Rail installer and
sales manager, to work up a slide rail system for use on the
project.
Efficiency's
Universal Slide Rail is a component shoring system comprised of
steel panels (similar to trench shield sidewalls) and vertical
steel posts. The system can be used in a variety of
configurations, such as small four-sided pits; large
unobstructed working pits as big as 50 feet by 50 feet with
Efficiency's ClearSpan System; or in a linear multi-bay
configuration to install length of pipe more than 40 feet.
Slide Rail is
installed simultaneously as the trench or pit is excavated by
sliding the panels into integrated rails on the posts — either
double or triple rails depending on needed depth — then pushing
the panels and posts incrementally down to grade as the pit is
dug; a process commonly referred to as a "dig and push" system.
The system is installed and removed incrementally, which allows
the trench to be properly shored throughout the entire
installation or removal process, always protecting workers from
a trench wall collapse.
"Slide rail works
because it keeps excavations tight and vertical with no loss of
dirt or fill," explains Ross.
The project was
located in hilly terrain, and the lift station, gravity
connector and force-main were to be installed more than 30 feet
deep in rocky Type C-60 soil. In order to reach that depth, East
Tennessee Grading benched down part way into the side of the
hill before excavating to grade. To handle the project, Brock
rented from Efficiency a four-sided 20-foot-by-20-foot pit
system which allowed crews to excavate the pit 24 feet deep to
reach grade. The entire excavation took up only a small area and
did not require as much backfill material.
"The slide rail
system was installed in a just one afternoon and removed in just
a half a day," explains Brock, adding that Efficiency's Greg
Ross also worked on the site and helped troubleshoot spots that
might have been troublesome.
"He literally
jumped into the hole and did not leave the site that evening
until the system was in," Brock says.
To complete the
project, East Tennessee Grading used Cat 345 and Cat 325
excavators to install the slide rail system and the
10-foot-diameter round, pre-cast lift station. A Cat D6 dozer
was also used on the project.
Brock and his
crew were able to install the entire wet well in one day, aside
from the cap which was subcontracted. All told, East Tennessee
Grading completed the 28-foot-deep wet well portion of the
project from beginning to end in just three days, and Brock
notes that the system "went in so much faster and a lot easier
than I was expecting."
The new lift
station was part of upgrade to the area's sewer system in
anticipation of more commerce in that area. The upgrade also
included elimination of an elevated sewer line that crossed a
nearby creek.
James McRay
March 19, 2007
Dixie Contractor
|