Tight quarters and concerns over stormwater
management bring unusual challenges to a retail project near
Cumming, Ga.
In many of Atlanta's northern
suburbs, retail projects are the bread and butter of many
commercial contractors. As populations grow, demand for such
projects increases — and one that's currently under construction
is the Shops of Windermere, a project being developed by Easlan
Capital of Atlanta, Inc., near Cumming, Ga.
The project, being constructed on
a 4-acre site, will feature 24,000 square feet of retail space.
General contractor is J.K. Lockwood Construction Company,
Alpharetta, Ga.
The building itself is a
straightforward structural steel structure which will be
finished with brick, stucco, stone, and structural masonry. But
other project elements — including an underground stormwater
retention pond and a challenging concrete block wall — presented
unusual sets of challenges for the construction team.
The
Wall
One challenge on this project
came in the form of a modular concrete block retaining wall
which was constructed along the back of the site. The wall
shores up a major cut along the back of the building complex, a
cut made necessary by the site's steeply sloping topography.
Originally, the wall was designed
as a cast-in-place concrete wall with a stone veneer applied to
areas that would be exposed to public view. However, the design
was changed to utilize modular block instead for reasons of cost
as well as feasibility.
The modular block wall, with an
overall length of about 850 feet and a maximum height of about
20 feet, is being constructed by Vecco, Inc., Alpharetta, Ga.,
using precast wall blocks from Keystone.
The wall sits atop a gravel sill
foundation. Excavation for the wall and for the sill was handled
by Triton Industries, Conyers, Ga., and one of the first
challenges faced during wall construction was the matter of what
to do with the excavated material. Plans called for using that
material as backfill once the wall was complete, but in the
meantime the only place to put it was on the building pad. Thus,
construction of the wall became an important part of the
scheduling operation, since building work could not get under
way until that excavated material was removed from the building
pad and placed as backfill.
The construction of the wall,
which is built at a slight batter, progressed smoothly. Crews
constructed it by placing several rows of block at a time, with
geogrid tied to the block at the start of construction of each
set of rows. The geogrid extended behind the wall for about 20
feet, and as each set of rows was completed the area behind the
wall was backfilled, anchoring the geogrid and securing the
wall. This process was repeated until the wall had reached the
desired height.
Two different block surfaces were
used, with more decorative facing on architecturally significant
portions of the wall.
The Underground Pond
A second challenge, and a major
factor during the site work phase, was construction of an
underground stormwater retention pond. Management of stormwater
runoff is an important issue on many projects. Frequently,
runoff is retained in surface ponds prior to controlled
discharge. However, where space is at a premium, other
approaches must be used.
At Windermere, for example, the
design includes an underground stormwater retention pond. As
originally designed, this would have been a 20-foot by 240-foot
cast-in-place value. However, value engineering yielded an
alternative utilizing precast concrete components — an
alternative which saved money as well as construction time. As
finally designed and constructed, the finished vault measures 42
feet wide and 121 feet long and has a height of 10 feet 9
inches. It will be totally buried (and totally out of sight)
once the project is completed.
Work on the pond began with
construction of concrete footings around the pond's perimeter —
but only after groundwater was brought under control.
"The original water table was 5
feet higher than the finished floor of the underground pond,"
notes project superintendent Mike Crossan, "so we had to put in
French drains to lower the water table." Triton Industries
handled the necessary excavation for drain installation (as well
as all other excavation on the project) using a Cat 330 and a
Cat 963.
Art's Concrete of Lawrenceville,
Ga., then began constructing the underground pond's perimeter
footings, which measure about 6 feet wide and 1 foot deep and
completely ring the perimeter. Concrete from Ernst Concrete was
placed directly from ready mix trucks, which accessed the pond
construction area via a ramp constructed at the west end of the
site.
The area inside the footings —
that is, the bottom of the underground pond — consists of a
1-foot lift of gravel sitting directly atop graded dirt.
Once footing work was finished,
crews from precast concrete supplier Metromont began assembling
the underground pond's precast wall sections. All precast
components were set by Superior Rigging & Erecting using a
70-ton crane. The wall sections, which were installed first, had
been manufactured with an inside lip at the top of each section.
Once the walls were in place, traffic-rated precast double tees
were set into position on the lips to form the "lid" atop the
underground pond.
"The largest precast piece
weighed about 32,000 pounds," notes Mike Crossan, superintendent
on the project, adding that installation went quickly.
"Metromont started placing
precast on a Thursday morning," he says, "and was finished by
Friday night."
A rubber membrane and tar were
used to seal the joints between wall panels inside and out, and
edges were grouted by hand. The exterior of the underground pond
was then backfilled, with fill compacted using a small roller
which could work close to the concrete walls.
To finish the underground pond,
the double-tees were subsequently overlaid with a 5-inch lift of
concrete reinforced with #4 and #6 bars. This resulted in a
traffic-rated roadway over the top of the underground pond,
necessary since the project's parking lot would subsequently be
constructed on top of it. Subsequent site work overlaid the
underground pond's concrete top with a foot of dirt, 6 inches of
crusher run stone, and 2 inches of asphalt to create the parking
area.
Water will enter the underground
chamber via one 36-inch pipe and two 18-inch pipes and will exit
the chamber through an outlet control structure with 1-inch
holes, pass through an oil and grit separator, then continue out
through a 24-inch pipe to a manhole located adjacent to the
nearby highway.
Staff
February 05, 2007
Dixie Contractor
|